Look for August opening of revamped Broadway bridge

Work continues on the rehabilitation of the Broadway bridge in downtown Fulton.

Gene Cilentro of the state Department of Transportation said the northside deck has been poured and continues to cure. The decorative railing was poured Thursday and Friday and then it must cure over the course of a few weeks.

“The project is 85 percent to 90 percent done,” Cilento said.

He said the sidewalks will be the last parts of the project to be done. The sidewalk on the north side will be done first and then lamp posts will be installed.

Cilento said one that sets, the full four lanes will open and then the sidewalk on the south side will go, probably in mid- to late August.

The new sidewalk has a cure time as well.

Share this story:
Facebook Twitter Pinterest Plusone Email

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>